Services/Dismantling, relocation, installation

Relocating production? The plant has to work at the new site.

Supervision of dismantling, relocation, installation and start-up of spray dryers and process lines.

Component preservation
01

Where the risk is

One lost drawing, one damaged part, one unlabelled pipe — and reassembly at the new site drags on for months.

02

What I do

  • Organise dismantling without damage
  • Label pipework and electrical cabinets
  • Control packing and preservation
  • Run installation and start-up at the new site
03

Projects

Line before dismantling Dismantling Component preservation Ready for shipment

Line before dismantling

Case 07Dairy industry, milk powder · Eastern Europe · 2021

Dismantling a process line for export — and a successful restart at its new site

Challenge

Dismantle the line — spray dryer, vacuum evaporator and powder storage silo — without damage, then pack and prepare it for export shipment.

    Root cause

    The company was selling the production line. The new owner had to reassemble and restart it at a different site, so any damage to components or loss of documentation would have made reassembly impossible.

      What was done

      As supervisor, organised and carried out all dismantling work.

      • All pipework and electrical cabinets were labelled
      • The equipment was packed and preserved for loading and transport

      Result

      The line was reinstalled and successfully commissioned at its new owner’s site.

      • The equipment was transported without damage
      • Labelling allowed the line to be reassembled at the new site without recreating the documentation
      Supervisor5 weeks
      Equipment delivery Chamber pre-assembly Foundation Drying chamber installation Equipment installation Building frame Cladding Finished production hall

      Equipment delivery

      Case 02Meat processing, animal protein powders · Eastern Europe · 2022 · General contractor

      A 4,500 m³ plant delivered turnkey — on second-hand equipment and a quarter of the original budget

      Challenge

      Build and commission a complete drying plant: spray dryer, powder storage silo, CIP station and cleaning system, and filling and packaging machine.

        Root cause

        The company dropped its bank investment loan and financed construction from working capital. With the budget cut fourfold, all equipment was bought second-hand — condition unknown and without engineering documentation for the new site.

          What was done

          Ran the project from procurement to start-up: work planning, installation supervision and commissioning.

          • As project manager, organised procurement of components, approved the plant layout and set up on-site fabrication of steel structures and assemblies
          • As supervisor, oversaw the mechanical and electrical installation of the process equipment and the building
          • As consultant, ran pre-commissioning diagnostics and resolved technical and process issues
          • Adjusted evaporation, atomisation and cleaning parameters and trained the operators

          Result

          The plant reached 100% of design capacity.

          • Full scope delivered: building construction, process line installation and commissioning
          • Product quality is consistent and in strong demand
          • The plant was built and commissioned without any bank financing
          Project manager · Supervisor · Consultant18 months

          Confirmed by a written reference from the plant owner

          Free express analysis

          A free express analysis of your dryer

          • The likely cause of the problem
          • What to check first
          • Whether a site visit is needed — or remote recommendations are enough

          Send photos and video — I’ll reply in writing within 3 working days.

          No calls, no obligations. NDA on request. Write in English or Russian.